Somehow, I have a feeling that BP will use this as a defense to stop any liability suits. Meanwhile the Obama regime, ever bowing to their corporate masters, continues to issue permits for deep water drilling in the Gulf of Mexico with absolutely no safe guards.

Tests on BP Well Blowout Preventer Confirm Redesign a Necessity

By Bob Cavnar at The Daily Hurricane

Yesterday, the Department of Interior released Det Norske Veritas’ (DNV) report on the forensic testing that it conducted on the blowout preventer (BOP) that failed to shut in BP’s blown out Macondo well almost a year ago.  I’m still going through the 500-plus page report to find answers to my many questions about the failed BOP, but I do agree with the over riding recommendation to the industry from DNV:

   “The finding of these studies should be considered and addressed in the design of future Blowout Preventers and the need for modifying current Blowout Preventers.”

DNV was addressing a recommendation to the industry that it study the causes and results of “elastic buckling” of the drill pipe within the Macondo BOP that pushed it to the side of the wellbore, preventing the blind shear ram, or the ram that is supposed to cut the pipe and seal the well, from doing so.  During the time of the blowout, the forces within the well were so strong that it lifted the drill pipe, causing it to buckle and push over to the side of the BOP bore, positioning it outside of the shearing faces of the rams.

BP Can Do More Tests on Deepwater Horizon Blowout Preventer, Court Rules

By Laurel Brubaker Calkins and Allen Johnson Jr. at Bloomberg News

BP Plc (BP/) can conduct additional tests on the Deepwater Horizon drilling rig’s blowout prevention equipment now that government examiners have finished their own forensic testing, a judge ruled.

“The additional BOP testing shall be performed in a manner that preserves the evidence to the maximum extent possible,” U.S. District Judge Carl Barbier said in his order, referring to the blowout prevention equipment. He ruled that other companies involved in the disaster could also now run additional tests, so long as everyone is allowed to monitor the procedures and share in the results.

The 300-ton stack of valves failed to seal off BP’s runaway well last April, triggering a fatal rig explosion and the worst offshore oil spill in U.S. history. BP asked Barbier for permission to partially dismantle and conduct laser scans on the blowout preventer, which was recovered from the sea floor off the Louisiana coast last year.

BP is clearly looking for any liability they can pin on the BOP,” said Houston lawyer Brent Coon, one of the lawyers marshalling evidence for the consolidated oil-spill damages lawsuits against BP and other companies involved in the failed drilling operation, referring to the blowout preventer.

(emphasis mine)

Deep Water Permits Issued With No Lessons Learned

In an exclusive investigation Rachel Maddow shows how the Department of the Interior is issuing deep water drilling permits despite a report finding the blow-out preventer design is flawed and despite drilling companies submitting emergency response plans that pre-date the Deep Water Horizon spill and therefore reflect none of the lessons of that disaster

1 comments

Comments have been disabled.